 Resource availability across projects, in Using Copper
 
dale.castro
 
PostPosted: Thu Apr 03, 2008 12:47 am    Post subject: Resource availability across projects Reply with quote
Joined: 01 Apr 2008
Posts: 5

Hey,

I watched the tour and it shows resources availability across projects when you add them as a resource to a task. When I do this on a task, all my resources time blocks are just grey (even if I create a brand new user that for sure hasn't been allocated). I can't actually book them any time. What am I doing wrong?

Thanks!
 
Ben
 
PostPosted: Thu Apr 03, 2008 12:55 am    Post subject: Reply with quote
Joined: 13 Mar 2003
Posts: 644

Check out the user guide at http://www.copperproject.com/guide.php

You need to set a user's availability first, this is done in the admin screen.
 
dale.castro
 
PostPosted: Thu Apr 03, 2008 4:51 am    Post subject: Reply with quote
Joined: 01 Apr 2008
Posts: 5

Thanks Ben,

That worked. The weird thing is that they were already set to 04/02/2008 - 04/02/2009 - Always. But after I set them again manually, it worked.

Thanks!
 