dale.castro |
Posted: Thu Apr 03, 2008 12:47 am Post subject: Resource availability across projects |
|
|
|
Hey,
I watched the tour and it shows resources availability across projects when you add them as a resource to a task. When I do this on a task, all my resources time blocks are just grey (even if I create a brand new user that for sure hasn't been allocated). I can't actually book them any time. What am I doing wrong?
Thanks! |
|
| |
|
 |
Ben |
Posted: Thu Apr 03, 2008 12:55 am Post subject: |
|
|
|
|
| |
|
 |
dale.castro |
Posted: Thu Apr 03, 2008 4:51 am Post subject: |
|
|
|
Thanks Ben,
That worked. The weird thing is that they were already set to 04/02/2008 - 04/02/2009 - Always. But after I set them again manually, it worked.