Xunil |
Posted: Wed Oct 24, 2007 7:18 pm Post subject: Linking projects |
|
|
|
As per thread title, is it possible to link projects ?
MS Project has the ability to link projects to a master project, or key tasks within a project to a master project.
Can Copper do anything along those lines ?
A client of mine in Holland wants to do this to manage several complex sub-projects under one master project and, so far, I've been unable to find an easy way to achieve this using Copper.
Any suggestions appreciated. |
|
| |
|
 |
MikeW |
Posted: Wed Oct 24, 2007 7:38 pm Post subject: |
|
|
Joined: 23 Oct 2007 Posts: 6 Location: Vancouver, Canada
|
I am new to Copper, but I wonder if the sub-tasks that allow allocation of different resources are not suitable. With a suitably broad project description at the top.
Is there a reason that using the sub-tasks in Copper is too clunky? (I am currently evaluating copper for my company) |
|
| |
|
 |
Ben |
Posted: Thu Oct 25, 2007 12:37 am Post subject: |
|
|
|
You sure can link projects, it is termed Related Projects within copper. From within a project you can edit it to add a related project, thereafter when you view the timeline that related project is also viewable in the timeline.
MikeW, the subtasks function isn't clunky, it behaves the same way other tools dictate, you select one or more tasks, hit the indent button (right-arrow) and it creates a subset for you.
Hope this helps! |
|
| |
|
 |
Xunil |
Posted: Thu Oct 25, 2007 10:15 am Post subject: |
|
|
|
| Ben wrote: |
You sure can link projects, it is termed Related Projects within copper. From within a project you can edit it to add a related project, thereafter when you view the timeline that related project is also viewable in the timeline.
MikeW, the subtasks function isn't clunky, it behaves the same way other tools dictate, you select one or more tasks, hit the indent button (right-arrow) and it creates a subset for you.
Hope this helps! |
Well thanks !
I guess I need to start digging a lot deeper - I didn't find that obvious at all, and I probably wouldn't have stumbled onto it for quite some time.
Thanks again  |
|
| |
|
 |
kkass |
Posted: Sat Dec 01, 2007 1:23 am Post subject: |
|
|
|
| Is there a way to make tasks in a project dependent on a task in a linked project? |
|
| |
|
 |
Ben |
Posted: Sat Dec 01, 2007 1:29 am Post subject: |
|
|
|
No, sorry.  |
|
| |
|
 |
Xunil |
Posted: Thu Jan 03, 2008 6:40 pm Post subject: |
|
|
|
| Ben wrote: |
You sure can link projects, it is termed Related Projects within copper. From within a project you can edit it to add a related project, thereafter when you view the timeline that related project is also viewable in the timeline.
MikeW, the subtasks function isn't clunky, it behaves the same way other tools dictate, you select one or more tasks, hit the indent button (right-arrow) and it creates a subset for you.
Hope this helps! |
Hmmmmmmm.......
I've been looking and looking and I can't seem to find the "related projects" function.
Where exactly is it ?
 |
|
| |
|
 |
Ben |
Posted: Thu Jan 03, 2008 11:12 pm Post subject: |
|
|
|
| Xunil wrote: |
Hmmmmmmm.......
I've been looking and looking and I can't seem to find the "related projects" function.
Where exactly is it ?
 |
In Corporate/Enterprise editions only, go to a project view/edit screen. |
|
| |
|
 |