Posted: Wed Oct 24, 2007 2:05 am Post subject: Copy a project, tasks' order is not the same as the original |
|
|
|
| Hi, this is not right. When copying a project, tasks' order is not the same as the original one's. I checked the database and found the sequence fields for the copied tasks are the same number. What is the logic there? Also what is the Indent field for? |
|
| |
|
 |
Ben |
Posted: Wed Oct 24, 2007 2:10 am Post subject: |
|
|
|
| Are you on a hosted account or licensed Daisy? Either way we have an updated version for you. |
|
| |
|
 |
daisy |
Posted: Wed Oct 24, 2007 2:31 am Post subject: |
|
|
|
We have a licensed copy, but we already did some customizations on it. There will be so much pain to customize another update. Can you send me details about what changed since 3521, so I can apply those changes?
Thanks in advance. |
|
| |
|
 |
Ben |
Posted: Wed Oct 24, 2007 2:44 am Post subject: |
|
|
|
We can send you the latest build, but as you might already be aware we can't support specific customizations.
There have been a number of customer-requested changes, and bug fixes, in the last month. Get in touch. |
|
| |
|
 |